Australia Post

Shared Services Facility Extension, 185 Rosslyn Street, West Melbourne VIC


1,200 m² / $2.2 million
Project Management & Superintendent Services


This project involved the extension and conversion of existing basement carparking into corporate offices at the Australia Post National Data Centre.

The process necessitated the establishment of an employee participation committee which was involved throughout the development of the design.

Works were programmed to ensure no disruption to the operations of the 24 hour a day facility.

The project received the 2000 Australian Institute of Building (AIB) ‘Award for Excellence in Project Management’ and 2001 Royal Australian Institute of Architects (RAIA) ‘Award for Interior Architecture’.