TRUenergy [Energy Australia]

Building Refurbishment & Fitout, 385 Bourke Street, Melbourne VIC


9,300 m² / $12.9 million
Project Management & Superintendent Services


Montlaur was engaged to assist TRUenergy with the base building refurbishment and fitout works to their headquarters at 385 Bourke Street.

Construction commenced in May 2010 involving a six stage handover to enable TRUenergy to remain in occupation throughout the duration of the works. Included in the staging was the construction of 2 separate tenancy stairs linking levels 28 to 30 and levels 32 to 34. While 4 of the 7 floors were new construction, the remaining existing floors required significant refurbishment and reconfiguration to provide an equitable workplace for all employees.

The project was successfully completed in July 2011 within the original program.